TM 5-4220-231-14&P
OPERATION
PROCEDURES
(OP) FOR DIVING OPERATIONS
OPERATOR CHECKLIST OP 9 (Charge
Primary Air) (Cont)
DATE -/-/
START TIME
END TIME
OPERATOR 1
OPERATOR
2
LOCATION
STEP
ITEM
LOCATION
ACTION
PERFORMED
CHECKED
IBY
BY
SECURE CHARGING OPERATIONS OP 9.5
NOTE
OP 9.5 should not be done until diving operations are completed.
9-5-1
AHP-V206
Primary DASS
Close CW.
Rack (with
AHP-V207
charging hose) -
Flask Valves
9.5.2
AHP-V208
Primary DASS
Slowly open CCW -
Rack (with
Turn back 1/4 CW.
charging hose)
9.5.3
AHP-V21 0
Primary DASS
Slowly open CCW bleeding all
Rack (with
pressure from system.
charging hose)
Close CW.
9.5.4
AHP-V208
Primary DASS
Close CW.
Rack (with
charging hose)
9.5.5
AHP-V208
Primary DASS
Remove Charging Hose.
Rack (with
Replace protective caps as
charging hose)
each hose is disconnected.
9.5.6
20 CFM HP
Approx. 100 ft.
Perform After Operation PMCS
Compressor
from primary
IAW TM 5-4310-389-14.
DASS Rack.
Conducted By:
Rank:.
Date/Time .
Verified By:
Rank:
Date/Time .
Supervior:
Rank:
Date/Time
.
Change 6