TM5-4220-231-14&P
OPERATION PROCEDURES (OP) FOR DIVINGOPERATIONS
OPERATOR CHECKLISTOP 2
DATE-/-/-
STARTTIME
END TIME
OPERATOR1
OPERATOR
2
LOCATION
STEP
ITEM
LOCATION
I
ACTION
PERFORMED
I CHECKED
IBY
BY
NOTE
8ft. Interconnecting Hoses shall be positioned between Top and Bottom DASS Racks during set-up.
NOTE
Secure and bleed pressure from Hoses prior to correcting leaks.
HOSE CONNECTIONS
OP 2.1
2.1.1
SDASS
Perform Before Operation
PMCS IAWTable 2-1
2.1.2
AHP-V203
Primary DASS
Connect 25/100 ft. HP hose at
Rack
AHP-V203 to DACC Primary
(Bottom Rack)
HP IN fitting.
Secure safety wires.
2.1.3
AHP-V209
Secondary
DASS
Connect 50/100 ft. HP hose at
Rack (Top Rack)
AHP-V209 to DACC
Secondary
HP IN fining.
Secure safety wires.
2.1.4
DACC
Rear DACC
Connect 2 ea. 4 ft. LP hoses to
LP OUT
Panel
VTA LP IN hose connections.
Fittings
Secure
safety wires.
2.1.5
Connect diving umbilicals (air
supply) to appropriate
red,
green, or yellow diver connector
on VTA flip up console.
2.1.6
Connect pneumo hose to
appropriate
pneumo fitting on
rear panel of DACC.
ENABLE PRIMARY DASS OP 2.2
2.2.1
AHP-V205
DASS Rack
Fully open CCW -
Turn back 1/4 CW.
2.2.2
AHP-V201
DASS Rack -
Slowly open fully CCW -
Front - Flask
Turn Back 1/4 CW.
AHP-V202
Valves
2.2.3
AHP-V203
DASS Rack
Slowly open CCW -
Turn back 1/4 CW -
Release
pressure
to DACC
Primary HP IN.
2.2.4
AHP-G211
DASS Rack
Record Pressure:
PSIG.
2-48